top of page

Site Plans:

Unincorporated Montgomery County:

NOVUS International

Engineering and site design for an agricultural research facility/farm.

First phase completed 2010.

Second phase currently in planning and design phase.

Loutre Market, Hwy 19 & Hwy 94, Montgomery County, MO

Commercial site plan, private on-site sewage disposal system design, and surveying for a gas station and convenience store.

Completed: 2004

Montgomery City:

AFB International

Engineering and site design for an animal research and testing facility.

Completed; 2009

Unincorporated Marion County:

Fastlane Taylor Truck Stop, Marion County, MO

Engineering design and site layout of a truck stop with an 18,000 GPD wastewater treatment facility.

Completed: 2009

Unincorporated St. Charles County:

Midwest Lawn & Landscaping

Engineering design and site layout for a commercial business.

Completed: 2011

Warrenton:

Market Street Cinema, Warrenton, MO

Commercial site design, including parking lot, building placement, grades, city street entrance, flood plain permits, and storm drainage w/ detention.

Completed: 2007

Warren County Historical Society

Design for building and parking lot expansion, underground storm water detention, and lighting upgrades.

Currently under construction.

Scenic Regional Library

Design for a parking lot expansion, underground stormwater detention & lighting upgrades.

Approximate Construction Cost: $120,000

Completed: 2009

St. John’s Lutheran Church

Design for building addition and parking lot expansion, above ground storm water detention, and site improvements.

Plans completed: 2011

College United Methodist Church

Design for building addition and parking lot expansion, and other site improvements.

Plans completed: 2009

Fastlane North

Commercial site design, including parking lot; building placement of a convenience store, gas pumps, and a car wash; grading; MoDOT entrance; storm drainage system with underground storm water detention; and construction staking.

Troy:

Fastlane

Commercial site plan, including parking lot; building placement of a convenience store, gas pumps, and a car wash; grading; MoDOT entrance; storm drainage with detention; and construction staking.

Domino’s Site Plan

Commercial site design for two buildings, including parking lot, grading, storm sewer design

Currently in design

Truesdale:

Boone’s Hollow Commerce Center

1263 LF of 8 inch x 28 feet reinforced concrete street with curb and gutter.

Construction Cost: $119,885

Funded in part by CDBG

Warrenton:

Market Street Cinema

Commercial site design, including parking lot, building placement, grades, city street entrance, flood plain permits, and storm drainage w/ detention.

Completed: 2007

Progress Bank

Commercial site design, including parking lot, grades, and storm drainage with detention.

Completed: 2006

Allegiant Bank

Commercial site design, including parking lot, grades, utility relocation and storm drainage w/ detention.

Jonesburg State Bank

Commercial site design, including parking lot, grades, and storm drainage with detention

Completed: 2006

Warrenton Area Industrial Park

Professional engineering and surveying services for construction of 2000 LF of concrete street with curb and gutter, 3940 LF of 8” water main extension, and 3768 LF of sanitary sewer extension, plus storm sewer design and inspection.

Wentzville:

HNB Bank

Commercial site design, including parking lot, building placement, grades, and storm drainage.

Completed: 2004

Twin City Marine

Commercial site design, including parking lot, building placement, grades, county road entrance, and storm drainage.

Alexander Industrial Park Spec Building

Commercial site design, including parking lot, building placement, grades, and storm drainage.

Gittemeier Office Building

Commercial site design, including parking lot, building placement, grades, and storm drainage.

Completed: 2007

Wright City:

Abel’s/McDonald’s

Commercial site plan design for a c-store and restaurant including street, storm, and water

Completed: 2002

Wright Center

Commercial site design for a strip mall including parking and grades

Completed: 2004

bottom of page